Case Study

Wine Bottling Line Relocation & Integration

From an operating bottling line in Italy to an integrated production system at its new destination.

Wine & Beverage | International Line Relocation

The Challenge

The customer needed to expand wine bottling capacity without waiting the potentially 12–18 months required for a completely new production line.

The solution also had to accommodate an extensive product portfolio, including different bottle formats, closures, labeling configurations, cartons and pallet formats.

Rather than starting with a predetermined machine, bXperts first established the technical and operational requirements, then searched internationally for an existing production line that could be adapted to the customer's needs.

Before beginning the equipment search, bXperts established the technical requirements covering available floor space, building height, electrical specifications, production flow, bottle and closure formats, labeling requirements, secondary packaging and current and future SKUs.

From Equipment Search to Production

  1. Equipment Selection & Due Diligence

    bXperts defined the production requirements and searched its international network for suitable operating bottling lines. Approximately three serious candidates were evaluated based on equipment condition, adaptability, maintenance history, logistics and required modifications.

    Preliminary engineering established whether each line could meet the customer's production requirements. The preferred line was then inspected while operating in Italy, followed by a joint customer inspection before the investment was finalized.

  2. Engineering & Modernization

    The existing line was re-engineered to meet the customer's production requirements. This included redesigning the layout, modifying the running direction of the filler/process block and integrating a new PE labeling machine.

    The palletizer also required automation redevelopment because the original software was unavailable. bXperts' automation engineers developed a modernization solution involving selected PLC/control component replacements and redevelopment of the required software.

  3. Dismantling & International Relocation

    A specialized bXperts team dismantled the operating line in Italy, systematically identifying equipment and connections and preparing the machinery for maritime transportation.

    At peak activity, approximately 25 personnel were involved, with dismantling and packing completed over approximately three to four weeks.

    Equipment was systematically identified, with cables and connections marked before disconnection and control backups secured where possible. Machinery was prepared for maritime transportation using industrial seaworthy crates, protective wrapping and moisture protection, applying the same care expected when shipping new production equipment.

  4. Installation, Commissioning & Ramp-Up

    Before installation, bXperts verified the destination facility's dimensions, equipment clearances, interfaces and utility readiness. Acting as the main contractor for the production-equipment and relocation scope, bXperts coordinated its activities with the customer and other contractors responsible for site infrastructure.

    At the destination, bXperts led the mechanical, electrical and automation work required to install and integrate the relocated and new equipment.

    The principal installation phase took approximately four to five weeks, followed by automation integration, commissioning and production ramp-up across the required formats and SKUs.

The Technical Challenges

Used-Equipment Evaluation

Technical due diligence to assess equipment condition, adaptability and required modifications before purchase.

Multi-Brand Integration

Integrating Krones, Heuft, PE and other equipment into one coordinated production system.

Legacy Automation

Redeveloping palletizer controls where access to the original software was unavailable.

High SKU Complexity

Accommodating multiple bottle, closure, labeling, carton and pallet configurations.

International Relocation

Dismantling, equipment preservation, shipping preparation, site readiness and coordination across multiple contractors.

The Result

The approximately USD 3 million project was delivered safely and on schedule, with rapid production acceptance and no major unresolved technical issues preventing progress.

According to subsequent customer experience, the relocated line became one of the strongest-performing lines at the destination in terms of efficiency and yield.

The project also established a continuing relationship, with bXperts supporting additional relocation, modification, consultancy and engineering assignments.

ON SCHEDULE

Project delivery

RAPID ACCEPTANCE

Production acceptance achieved quickly

12 MONTHS

Post-commissioning technical support

Beyond Commissioning

The project did not end at production acceptance.

At the customer's request, bXperts maintained approximately one to two specialists on-site for an additional 12 months.

Their work included local technician training, establishing preventive-maintenance practices, implementing optimization modifications, supporting new recipes and SKUs, and transferring technical knowledge to the customer's team.

This extended support helped the customer establish reliable operation and develop the internal capabilities needed to maintain and optimize the relocated line.

Capabilities Behind the Project

Line Relocations

Planning and executing production line moves.

Learn More: Line Relocations

Equipment Integration

Integrating new & relocated equipment into production.

Learn More: Equipment Integration

Automation & Electrical

Controls, electrical integration & automation support.

Learn More: Automation & Electrical

M&E Installations

Installation and technical execution at the destination.

Learn More: M&E Installations

Project Management & Engineering

Project, engineering & multidisciplinary coordination.

Learn More: Project Management & Engineering